Hello,

This may be a silly question. When setting the job durations for each job type. Should these durations include drive time? Or just actual working time required?

Thank you,

Michelle Brown 

1 REPLY 1

robert_y
New Contributor II

We set up the job times for the estimated duration of performing the actual job.  Dispatch Pro should be calculating any drive times between the jobs.  Hope this helps!