09-17-2019 02:42 PM
We are working on trying to make a nice streamlined system for tracking a permit as it goes through processing to inspection to excavation to resolution, etc. I thought about listing the steps in one note on the job, then just editing as each step gets done, but there s a concern about having too much minutiae when the plumbers are trying to check back through the job notes. Do you have any suggestions?
10-11-2019 11:16 AM
Sure thing! You've inspired me to do this also. Thank you!
12-20-2022 08:36 PM
Do you guys have a screenshot of your dispatch with examples of these pending tags you wouldnt mind sharing?
10-11-2019 11:14 AM
Thank you, Maria! We did add some but need some of these that you recommended, also!
10-11-2019 10:50 AM
Maybe create tags and edit those tags on the job as they change? "Permint Pending" "Permit Pulled" "Inspection needed" "Inspection Passed" "Inspection failed" "Final Inspection Needed" ETC.